CONTENTS

1..... Introduction.. 1

1.1     Background. 1

1.2     Objectives of the Silt Curtain Deployment Plan. 1

1.3     Overview of Silt Curtain Deployment 2

2..... Design of Silt Curtains.. 3

2.1     Cage-type Silt Curtain. 3

2.2     Floating Silt Curtain. 4

3..... Installation of Silt Curtains.. 8

3.1     Cage-type Silt Curtain. 8

3.2     Floating Silt Curtain. 8

3.3     Works Activities requiring Deployment of Silt Curtains. 8

4..... Testing of Silt Curtains.. 9

4.1     Background of the Pilot Test 9

4.2     Arrangement for Pilot Test 9

4.2.1     Locations of Pilot Test 9

4.2.2     Testing Parameters for Pilot Test 12

4.2.3     Timing and Duration. 12

4.2.4     Reporting. 13

4.3     Determination of Silt Curtain Efficiency. 13

5..... Operation and Maintenance of silt curtain.. 14

 

Annexes

Annex A      Silt Curtain Daily Inspection Checklist

Annex B      Underwater Inspection Checklist

Annex C      Implementation Schedule of Recommended Mitigation Measures

Annex D      Details of Manufacturer/ Supplier’s Specification and Project References

 

List of Tables

Table 2.1    Specification of the Proposed Geotextile. 7

Table 3.1    Locations of Deployment of Silt Curtain.. 8

Table 4.1    Indicative Monitoring Locations for Cage-type Silt Curtain during Dredging and Jetting  9

Table 4.2    Indicative Monitoring Locations for Floating Silt Curtain.. 11

Table 4.3    Testing Parameters and Equipment for Pilot Test 12

 

List of Figures

Figure 1.1   Indicative Location of Key Project Components

Figure 1.2   Specific Location of the Pipeline Construction Works requiring Deployment of Floating Double Layer Silt Curtain

Figure 2.1   Cage-type Silt Curtain Indicative Design

Figure 2.2   Typical Arrangement of Cage-type Silt Curtain

Figure 2.3   Indicative Arrangement of Floating Silt Curtain

Figure 2.4   Indicative Arrangement of Floating Silt Curtain in Sections

Figure 4.1   Indicative Monitoring Locations for Cage-type Silt Curtain during Dredging and Jetting

Figure 4.2   Indicative Monitoring Locations for Floating Silt Curtain

 

 


1.             Introduction

1.1        Background

To support the increased use of natural gas in Hong Kong from 2020 onwards, Castle Peak Power Company Limited (CAPCO) and The Hongkong Electric Co., Ltd. (HK Electric) have identified that the development of an offshore liquefied natural gas (LNG) receiving terminal in Hong Kong using Floating Storage and Regasification Unit (FSRU) technology (‘the Hong Kong Offshore LNG Terminal Project’) presents a viable additional gas supply option that will provide energy security through access to competitive gas supplies from world markets.  The Hong Kong Offshore LNG Terminal Project will involve the construction and operation of an offshore LNG import facility to be located in the southern waters of Hong Kong, a double berth jetty, and subsea pipelines that connect to the gas receiving stations (GRS) at the Black Point Power Station (BPPS) and the Lamma Power Station (LPS).

The Environmental Impact Assessment (EIA) Report for the Hong Kong Offshore LNG Terminal Project was submitted to the Environmental Protection Department (EPD) of the Hong Kong Special Administrative Region Government in May 2018.  The EIA Report (EIAO Register No. AEIAR-218/2018) was approved by EPD and the associated Environmental Permit (EP) (EP-558/2018) was issued in October 2018.  An application for Further Environmental Permits (FEP) was made on 24 December 2019 to demarcate the works between the different parties.  The following FEPs were issued on 17 January 2020 and the EP under EP-558/2018 was surrendered on 5 March 2020:

§   the double berth jetty at LNG Terminal under the Hong Kong LNG Terminal Limited, joint venture between CAPCO and HK Electric (FEP-01/558/2018);

§   the subsea gas pipeline for the BPPS and the associated GRS in the BPPS under CAPCO (FEP-03/558/2018); and

§   the subsea gas pipeline for the LPS and the associated GRS in the LPS under HK Electric (FEP-02/558/2018).   

The location plan for the works associated with the subsea gas pipeline for LPS and the associated GRS in LPS (‘the Project’) is provided in Figure 1.1.

 

1.2        Objectives of the Silt Curtain Deployment Plan

This Silt Curtain Deployment Plan for the Project has been prepared in accordance with Condition 2.10 of the Further Environmental Permit FEP-02/558/2018.

FEP No. FEP-02/558/2018, Condition 2.10:

“The Permit Holder shall, no later than 1 month before the commencement of marine works including construction of the subsea gas pipeline, deposit with the Director 3 hard copies and 1 electronic copy of a silt curtain deployment plan. The silt curtain deployment plan shall include but not limited to the details of the design, installation, testing, operation and maintenance of the silt curtains to be deployed during construction of the Project to avoid and minimize the water quality impact due to the dredging and jetting works for laying and burying the subsea gas pipeline. Pilot tests on the efficiency of silt curtain system shall be conducted during the early stage of construction to confirm the removal efficiency of the silt curtains. The deposited silt curtain deployment plan shall be fully and properly implemented during construction of the Project.”

The key objective of this Silt Curtain Deployment Plan is to include the details of the design, installation, testing, operation and maintenance of the silt curtains to be deployed during construction of the Project to avoid and minimize the water quality impact due to the dredging and jetting works for laying and burying the subsea gas pipeline.  Based on the latest design, the pre-installed pipeline at KP 17.4 will be used for the LPS Pipeline tie-in and cofferdam construction works are not required for the LPS Pipeline shore approach.  Therefore, this Silt Curtain Deployment Plan focuses on the silt curtains to be deployed for the dredging and jetting works for the Project.

The Silt Curtain Deployment Plan will be reviewed and updated as appropriate, throughout the course of the construction works to confirm that it remains current with the latest detailed information and works practice.

 

1.3        Overview of Silt Curtain Deployment

As stipulated in Condition 3.3 of FEP-02/558/2018, silt curtains shall be properly installed, tested, operated and maintained during construction of the subsea gas pipeline in accordance with the Silt Curtain Deployment Plan deposited under Condition 2.10 of FEP-02/558/2018.  Cage-type silt curtain shall be installed enclosing the grab dredger and jetting machine during construction of the subsea gas pipeline.  No silt curtain installation shall encroach onto the existing marine parks and the proposed South Lantau Marine Park.

Two types of silt curtains will be deployed for the dredging and jetting works of the Project:

§   Cage-type silt curtain will be installed enclosing the grab dredger / jetting machine during dredging / jetting works for the construction of the subsea gas pipeline; and

§   Floating double layer silt curtain will be deployed prior to the jetting works at KP0.1 – KP5.0 in order to minimize potential water quality impacts of the proposed South Lantau Marine Park.  Specific location of the pipeline construction works requiring the deployment of floating double layer silt curtains is illustrated in Figure 1.2.  The floating double layer silt curtain will be deployed outside the eastern boundary of the proposed South Lantau Marine Park.


 

2.             Design of Silt Curtains

2.1        Cage-type Silt Curtain

Cage-type silt curtain will be installed for dredging and jetting activities for the pipeline construction works.  A cage-type silt curtain consists of a layer of geotextile tied on a steel pipe surface buoyancy frame with pipe diameter of ~1,000 mm.  The geotextile will be secured from water surface to seabed level by steel chain ballast.  Sufficient length of the geotextile will be provided such that the silt curtain can be extended from the water surface to the seabed level during high tide condition.  Silt curtain with various curtain depth and curtain strength of around 110 kN/m will be deployed.  The bottom part of the silt curtain will be kept away from the seabed by a distance of ~0.3m in order to avoid disturbing the seabed.  The indicative design of cage-type silt curtain is illustrated in Figure 2.1 and the typical arrangement of cage-type silt curtain installed on a work barge is illustrated in Figure 2.2.

Figure 2.1      Cage-type Silt Curtain Indicative Design

77cbebdc141b4e38b71d25e9501fc55

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remark:  The shape and dimension of the cage-type silt curtain are indicative and subject to modification depending on site conditions.

 

Figure 2.2      Typical Arrangement of Cage-type Silt Curtain

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.2        Floating Silt Curtain

Floating silt curtain will be deployed along the eastern boundary of the proposed South Lantau Marine Park during the jetting works at Double Berth Jetty to South of Shek Kwu Chau (KP0.1-5.0).  No silt curtain installation will encroach onto the existing and proposed marine parks.

The floating silt curtain consists of two layers of geotextile mounted onto polystyrene foam float with diameter of ~500 mm with polyethylene protective hard shell cover.  The geotextile will be extended slightly above the seabed level and secured by steel chain ballast or equivalent (e.g. concrete sinkers) to avoid the bottom part of the silt curtain from touching the seabed and causing unnecessary disturbance of seabed sediment.  The bottom part of the silt curtain will be kept away from the seabed by a distance of ~0.3m in order to avoid disturbing the seabed.

The length of the silt curtain deployed at the active jetting location will be determined considering the findings of the EIA Report, the potential impact to existing marine traffic for review by the Marine Department and the performance of the pilot test (see details in Section 4) upon agreement with the Environmental Team (ET) and the Independent Environmental Checker (IEC). The floating silt curtain will be pulled at both ends by tug boats to maintain tension. Surface structure of the floating silt curtain will be linked to a towing rope instead of being towed by motor tugs directly for manoeuvring in order to reduce the tension of the floating silt curtain during towing.  Flashlight will be installed on marker buoys and tug boats for alerting marine operators at night.  Should the floating silt curtain be necessary to be separated into sections, a distance of ~150m overlapping between two sections of the floating silt curtain will be maintained as far as practicable to mitigate potential water quality impacts between two floating silt curtain sections.  The floating silt curtain will be shifted during jetting depending on the location of jetting operation.  Should there be any unacceptable water quality impacts to the water sensitive receivers at the proposed South Lantau Marine Park from the impact water quality monitoring, the Contractor(s) will propose remediation measures (e.g. checking of silt curtain integrity, extension of floating silt curtain) in consultation with the ET and the IEC. 

The indicative arrangement for floating silt curtain is illustrated in Figure 2.3.  The indicative arrangement for floating silt curtain in sections is illustrated in Figure 2.4.  The specification of the proposed geotextile is shown in Table 2.1.  The details of manufacturer / supplier’s specifications and project references are shown in Annex D.

Figure 2.3      Indicative Arrangement of Floating Silt Curtain

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Notes:

1) Preliminary 1000m length, subject to site conditions and trial.

2) Distance between silt curtain and metal frame will be subject to site condition and trial.


 

Figure 2.4      Indicative Arrangement of Double Layer Silt Curtain in Sections

 

 

 

 

 

 

 

 

Table 2.1        Specification of the Proposed Geotextile

Technical Data Sheet

Polymer

Density

Melting Point

Construction

100% Polypropylene

0.91 kg/dm3

165 °C

Tapes

Properties

Mechanical Properties

Standard

Performance

Tolerance

Tensile strength - MD

EN ISO10319

110 kN/m

-9.9 kN/m

Tensile strength - CMD

EN ISO10319

110 kN/m

-9.9 kN/m

Elongation at maximum load - MD

EN ISO10319

10 %

+/- 2.3 %

Elongation at maximum load - CMD

EN ISO10319

8 %

+/- 1.8 %

Static puncture resistance (CBR)

EN ISO12236

12.5 kN

-2.5 kN

Dynamic perforation resistance (cone drop)

EN ISO13433

10 mm

+2.0 mm

Tensile strength at 2% elongation - MD

EN ISO10319

15 kN/m

 

Tensile strength at 2% elongation - CMD

EN ISO10319

25 kN/m

 

Tensile strength at 5% elongation - MD

EN ISO10319

45 kN/m

 

Tensile strength at 5% elongation - CMD

EN ISO10319

60 kN/m

 

 

Hydraulic Properties

 

Standard

 

Performance

 

Tolerance

Water permeability normal to the plane (Vlh50)

EN ISO11058

25 l/m2s

-8 l/m2s

Characteristic Opening Size (O90)

EN ISO12956

230 µm

+/- 69.0 µm

Physical Properties

Standard

Performance

Tolerance

Weight

EN ISO9864

464 g/m2

+/- 46.4 g/m2

Length (+/- 1%) x width (+/- 1%)

-

100 x 5.25 m

-

Truck Load Volume (+/- 10%)

-

30,450 m2

-

Roll diameter (+/- 10%)

-

45 cm

-

Durability

Standard

Performance

Predicted minimal durability in years in natural soils with 4 <pH < 9 and soil temperature <25°C

EN ISO13438 - A2

25 years

Maximum allowed time between installation and covering of the geosynthetic

EN 12224

2 weeks

 

 


3.             Installation of Silt Curtains

3.1        Cage-type Silt Curtain

Cage-type silt curtain will be fixed and hung underneath the frame by nylon rope on deck of crane barge after the completion of fabrication of steel buoyancy frame.  The skirt of cage-type silt curtain will be coiled by tightening rope for easy deployment.

The entire steel buoyancy frame with cage-type silt curtain will be lifted and erected to the grab dredger or jetting machine when the rigging structure or mounting brace is ready.  The coiling ropes will be cut at the steel buoyancy frame and the curtain skirt will be released to the seabed for enclosure.

Cable ropes pre-installed at the bottom of the cage-type silt curtain will be lifted up and tightened at the steel buoyancy frame to adjust the depth of curtain skirt on site from time to time.

 

3.2        Floating Silt Curtain

Floating silt curtain will be delivered to the location for fixing by flat top/crane barge.  All vertical joints of each span of the floating silt curtain will be connected and tied up and coiled with ropes in a tube-form pattern by workers working on deck of the barge. 

Steel chain ballast or equivalent (e.g. concrete sinkers) will be deployed at the designated positions along the route by crane barge equipped with real-time global positioning system when the position of floating silt curtain is confirmed.

One of the ends of the towing rope will be picked up and the floating silt curtain will be lowered down slowly into the water by the main towage front tug when the floating silt curtain is available for deployment.

Coiling rope will be cut by small work boat, and the curtain skirt and ballast chain will be released into the water after the other end of towing rope is secured at the back tug and all tugs are in position.

 

3.3        Works Activities requiring Deployment of Silt Curtains

The works activities (i.e. dredging / jetting works) requiring deployment of silt curtains in the corresponding locations are shown in Table 3.1.

 

Table 3.1        Locations of Deployment of Silt Curtain

Work Location

Cage-type Silt Curtain

Floating Silt Curtain

LPS Pipeline Riser

(LPS KP0.0-0.1)

Yes

No

Double Berth Jetty to South of Shek Kwu Chau

(LPS KP0.1-5.0)

Yes

Yes (at Eastern Boundary of the Proposed South Lantau MP)

South of Shek Kwu Chau to West Lamma Channel

(LPS KP5.0-14.5)

Yes

No

West Lamma Channel

(LPS KP14.5-17.4)

Yes

No

 


 

4.             Testing of Silt Curtains

4.1        Background of the Pilot Test

As stated in Condition 2.10 of FEP-02/558/2018 and Section 5.3.2 of the Updated EM&A Manual of the Hong Kong Offshore LNG Terminal Project, pilot tests on the efficiency of silt curtain system shall be conducted during the early stage of construction to confirm the removal efficiency of the silt curtains.  The pilot test will be conducted by measuring turbidity and suspended solids (SS) at selected stations within and outside silt curtains to be discussed below. 

The pilot test on silt curtain systems will include the following tests:

§   Silt curtain at grab dredger (testing of silt removal efficiency of 75% or higher);

§   Silt curtain at jetting machine (testing of silt removal efficiency of 85% or higher); and

§   Double layer of silt curtains at sensitive receivers (testing of silt removal efficiency of 80% or higher).

The results of the pilot tests to be conducted during the early stage of construction will be applicable to dredging / jetting works for the Hong Kong Offshore LNG Terminal Project, i.e. the subsea gas pipeline for BPPS under FEP-03/558/2018 and the subsea gas pipeline for LPS under FEP-02/558/2018. 

 

4.2        Arrangement for Pilot Test

During the pilot test, dredging/ jetting works shall be actively undertaken within the works areas with the silt curtains deployed, and shall be operated at or close to the maximum productivity.  The surrounding environment will be controlled as far as practicable such that there would be no other major construction activities with potential of generating suspended solids being operated concurrently.

 

4.2.1  Locations of Pilot Test

The pilot test covers two different types of silt curtains proposed, the cage-type silt curtain and the floating silt curtain.

 

4.2.1.1           Cage-type Silt Curtain during Dredging and Jetting

There will be five monitoring stations of which one will be inside the cage while the rest will be outside the silt curtain in four directions.  The indicative monitoring locations for cage-type silt curtain during dredging and jetting are shown in Table 4.1 and Figure 4.1.

 

Table 4.1 Indicative Monitoring Locations for Cage-type Silt Curtain during Dredging and Jetting

Monitoring Station

Location

Description

A1

Within silt curtain

One monitoring station will be located inside the cage

B1

Outside silt curtain

Four monitoring stations will be located at four sides of silt curtain and within ~50 m from the silt curtain boundary

B2

B3

B4

Remark:  Each applicable station will be sampled and measurements/ water samples will be taken at three depths, 1m below the sea surface, mid-depth and 1m above the seabed.  For stations that are less than 3m in depth, only the mid-depth sample shall be taken.  For stations that are less than 6m in depth, only the sea surface and bottom samples shall be taken.  For in-situ measurements, duplicate readings shall be made at each water depth at each station.  Duplicate water samples shall be collected at each water depth at each station.

 

Figure 4.1      Indicative Monitoring Locations for Cage-type Silt Curtain during Dredging and Jetting

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Note:             The actual monitoring locations will be determined on site considering the locations of the cage-type silt curtain, anchor wires of the barges and nearby marine traffic conditions.

 

 

4.2.1.2           Floating Silt Curtain

There will be six monitoring stations of which three will be near the marine works area while the rest will be at the other side of the silt curtain.  As the floating silt curtain will be placed at water sensitive receivers, the distance between the emission source and the silt curtain for the pilot test is expected to be ranged from ~20 m to ~100 m depending on the location where the pilot test will be conducted in the vicinity of water sensitive receivers (e.g. the proposed South Lantau Marine Park).  The indicative monitoring locations for floating silt curtain are shown in Table 4.2 and Figure 4.2.

 

 

Table 4.2        Indicative Monitoring Locations for Floating Silt Curtain

Monitoring Station

Location

Description

A1

Near marine works area

Three monitoring stations will be ~50 m apart from each other and situated between marine works area and the silt curtain boundary

A2

A3

B1

The other side of silt curtain

Three monitoring stations will be ~50 m apart from each other and situated at ~50 m from the other side of silt curtain boundary

B2

B3

Remarks:

1) Each applicable station will be sampled and measurements/ water samples will be taken at three depths, 1m below the sea surface, mid-depth and 1m above the seabed.  For stations that are less than 3m in depth, only the mid-depth sample shall be taken.  For stations that are less than 6m in depth, only the sea surface and bottom samples shall be taken.  For in-situ measurements, duplicate readings shall be made at each water depth at each station.  Duplicate water samples shall be collected at each water depth at each station.

2) Measurements/ water samples will be taken at representative tidal condition during which the direction of water currents will be from marine works area towards silt curtain.

 

 

Figure 4.2      Indicative Monitoring Locations for Floating Silt Curtain

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Note 1:        The distance will depend on the location where the pilot test will be conducted in the vicinity of water sensitive receivers.

 

4.2.2  Testing Parameters for Pilot Test

The testing parameters for the pilot test are shown in Table 4.3.  Other relevant data will also be measured and recorded during the pilot test, including the location of the monitoring stations, water depth, time, weather conditions, sea conditions, tidal state, current direction and velocity, special phenomena and dredging / jetting rate during the pilot test.  The monitoring equipment to be used, sampling / testing protocols, laboratory measurement and analysis will follow the requirements as stated in the Updated EM&A Manual. 

Table 4.3       Testing Parameters and Equipment for Pilot Test

Parameter

Unit

Abbr.

Equipment

Reporting Unit

In-situ measurements

Turbidity

NTU

-

Instrumental, CTD

0.1

Laboratory measurements

Suspended solids

mg L-1

SS

APHA 2540E

1.0

 

 

 

 

 

4.2.3  Timing and Duration

The pilot test will be scheduled to be conducted during the early stage of construction:

§   three rounds within a single monitoring day covering mid-ebb and mid-flood tides for cage-type silt curtain for dredging works.  Each round of monitoring will be conducted when dredging works are operated at or close to the maximum productivity and the measurement at each monitoring station between any two rounds will be separated by at least 1 hour.  The monitoring will be scheduled when relatively high current speed condition is expected on the day of testing, as far as practicable;

§   three rounds within a single monitoring day covering mid-ebb and mid-flood tides for cage-type silt curtain for jetting works.   Each round of monitoring will be conducted when jetting works are operated at or close to the maximum productivity and the measurement at each monitoring station between any two rounds will be separated by at least 1 hour.  The monitoring will be scheduled when relatively high current speed condition is expected on the day of testing, as far as practicable; and

§   three rounds within a single monitoring day for floating silt curtain.  Each round of monitoring will be conducted when jetting works are operated at or close to the maximum productivity and the measurement at each monitoring station between any two rounds will be separated by at least 1 hour.  The monitoring will be scheduled when the representative tide with relatively high current speed condition is expected on the day of testing, as far as practicable.  Measurements/ water samples will be taken at representative tidal condition during which the direction of water currents will be from marine works area towards silt curtain for the pilot test for floating silt curtain.

Given the monitoring design of the pilot test is to measure near-field water quality around the emission source to determine the silt-retaining effectiveness of the silt curtain system, the proposed pilot test monitoring frequency (i.e. three rounds within a single monitoring day when relatively high current speed condition is expected on the day of testing and during representative tide with relatively high current speed condition which the direction of water currents will be from marine works area towards floating silt curtain to represent worst case scenario for the silt curtain system in terms of the silt-retaining capacity and integrity) is considered adequate.

During the pilot test, the dredging / jetting works shall be actively conducted within the works areas at a representative work rate not exceeding the allowed maximum work rate as stated in the Updated EM&A Manual.  The surrounding environment should be controlled as far as practicable such that there would be no other major SS-generating construction activity operating concurrently in the vicinity that may influence the pilot test results.

 

4.2.4  Reporting

Considering that the pilot test will be conducted during the early stage of construction, the findings of the pilot test will be reported in the corresponding monthly EM&A report for the month in which the pilot test would be conducted, and the following information will be reported:

§   Location plan(s) showing the monitoring stations for the corresponding silt curtains;

§   Results of in-situ and laboratory measurement (in summary and full dataset); and

§   Findings from the evaluation of pilot test results and recommendations for improvements, if any.

 

4.3        Determination of Silt Curtain Efficiency

Silt curtain efficiency is determined by the difference between the SS level ([1]) near marine works area and that outside silt curtain.  The following equation is adopted to determine silt curtain efficiency:

 

where, SS (inside) is determined by averaging the SS levels inside the marine works area (e.g. the average of A1 to A3 for floating silt curtain); SS (outside) is determined by averaging the SS levels at monitoring stations outside the silt curtains (i.e., the average of B1 to B3 for floating silt curtain; the average of B1 to B4 for cage-type silt curtain).

Should the efficiency of the silt curtain system to be adopted did not satisfy the requirements in the approved EIA Report, the Contractor shall propose further measures / improvements to the silt curtain system for consideration by HK Electric, the ET and the IEC.  However, regardless of the measured efficiency of the silt curtain system, the Event and Action Plan established in the Updated EM&A Manual shall only be based on the monitoring results of the construction phase water quality monitoring at the impact monitoring stations.


 

5.             Operation and Maintenance of silt curtain

The Contractor will check the condition of the silt curtain (both cage type and floating silt curtain) before commencement of works every day. Refuse around the silt curtains will be collected regularly and as needed on a daily basis so that water behind the silt curtains will be kept free from floating debris.  Sufficient spare geotextile will be kept on site for replacing damaged silt curtains.  The spare geotextile shall be kept appropriately to avoid direct contact with water and sunlight.

Underwater silt curtain inspection will be carried out after adverse weather (e.g. Typhoon Signal No. 3 or above).  Underwater silt curtain inspection will also be conducted after installation / re-installation / relocation of silt curtains / suspected sediment release due to ineffectiveness of silt curtain (e.g. from the impact water quality monitoring results to be conducted by the ET, observations by the Contractor(s), HK Electric, ET or IEC).  Underwater silt curtain inspections shall cover at least a 10m length of silt curtain or one whole silt curtain panel (whichever is greater) at each location, and at intervals of at least every 200m along the length of silt curtains deployed.  The underwater inspections shall check that the silt curtain fabric is intact, the silt curtain depths and ballast weight (for cage-type silt curtain) and steel chain ballast or equivalent (e.g. concrete sinker) (for floating silt curtain) positions are correct, and there is no damage / breakage in ballast weights/ steel chain ballast or equivalent and load lines.  Photographic records shall be taken during each underwater inspection.  All identified defects / damage shall be photographed and the position recorded on GPS to enable the affected areas to be subsequently located for in-situ repair where appropriate.  An inspection checklist will be prepared and filled in by the Contractor, and endorsed by HK Electric.  All checklists will be kept on site for record purpose.

In the event of silt curtain being damaged and/or requiring repairing works at the corresponding works locations, the related dredging / jetting works will be suspended immediately until the rectification works for the silt curtain is completed subject to the satisfaction by HK Electric.

Samples of Silt Curtain Daily Inspection Checklist and Underwater Inspection Checklist are shown in Annex A and Annex B, respectively.



 

 



[1]              Turbidity may also be used to determine silt curtain efficiency as necessary.